Proposed project to improve public lighting in Sarrià de Ter

Technical and energetic audit of the public lighting of the municipality. Proposal for improvement and economic valuation.

  • Client
    • Ajuntament de Sarrià de Ter / Diputació de Girona
  • Year
    • 2016
  • Phase
    • Finalitzat
Technical and energy audit of public lighting of the municipality analyzing the feasibility and performance of the different proposals focused on reducing energy consumption and associated 
economic cost. The feasibility of externalizing the implementation of the improvement through a contract with an energy services company has also been analyzed.
The overall saving achieved is 70% of the total consumption of public lighting, with an investment amortization of 3.2 years.